Report from our correspondent (reporter Shen Minggao) recently, triumpher
steel construction to undertake the Malaysian rapid project. The project is
built by Petronas large-scale oil refining and chemical integration project,
based on the needs of Southeast Asia's growing oil and chemical raw materials
demand. Project is located in Malaysia in the soft edge garland in Florida
Pengerang area. Take Sinopec refinery project scope of work includes 15 million
tons / year atmospheric distillation unit, 880 million tons / year of residual
oil hydrogenation plant, hydrogen collection and distribution device and fuel
oil system. Triumpher steel construction group to undertake is the residue
hydrotreating unit, hydrogen collection and distribution device and fuel oil
system, the largest Gallery parts of steel structure.
The project works out
to about 4000 tons, scope of work includes the European standard (BS EN) node
design, second deepening, processing, packaging and FOB port of delivery.
Difficult project is the European standard manufacture standard, American
Welding Society AWS welding requirements and Anst inspection project suitable
shipping packaging and two-dimensional code component management and PMC project
management model.
In order to realize the project started smoothly and
successful delivery, technology and qualification bottleneck triumpher steel
construction management team to focus on the beginning stage of the project meet
the European standard design and processing requirements, to invite the third
party MOODY first to provide technical services to solve the welding technology
assessment of the project implementation of AWS, according to the welder welding
method, using the actual project in the material level, welding position and
thickness of base material, the test in accordance with AWS D1.1/D1.1M
requirements, and obtain the corresponding welding certificate; qualification
certificate ANST inspection personnel training and examination to obtain the
project required; secondly, the first encounter in the process of BS EN 1090-2
manufacture requires detailed digestion the absorption, implement the technical
clarification processing factory, approval on the EXC-2/3 level requirements do
research and processing with the implementation of the project participants
Member can be started in the former do have the corresponding qualifications of
personnel, technical requirements for processing clear; after Malay project team
of the company's efforts, the project on April 22, successfully launched a
project to start the pre inspection meeting, the compilation of the project
procedures in before the start of the project has been submitted timely and
effectively implemented.
Currently, the project has solved the technical
qualifications required by the European standard overseas projects and items of
export packaging requirements and component delivery management of
two-dimensional code management system, a series of operational problems. The
Malay project, the first batch of members after the pre inspection meeting
smoothly. At this stage first structure pieces about 500 tons has comprehensive
processing. Plan on May 25, began delivery and in early June arrived in Malaysia
Johor project site