Urumqi railway station building of spherical grid began to ascend
Source:  Date:2015-07-29 15:08:07  Author:
 

In June, Urumqi railway station housing system assembled into the peak, in South Station building of the spherical grid section for a total of nine promotion, 13, 14, 15 lifting section respectively on June 3 to June 8, completed to enhance the work, now three lifting section has been transferred to enhance the air between the worthy to fill in the rod connected and connected with a base fixed work, other six lifting section have been carried out at the same time, ground assembly work, as of the end of June, six lifting section has been completed 75% of the ground assembly work, for a mid July promotion ready.

(correspondent Wang Changgang)